Construction of Bangladesh's Matarbari Port is progressing on schedule, with about 3.6 million cubic metres of dredging completed so far, Shipping Minister Shaikh Rabiul Alam told parliament on Tuesday.
Work has started on two of the project's three main packages. The contractor for civil works received its notice to proceed on 31 August, and equipment for land reclamation is on site, with geotube embankments, dredging and sand filling under way, the minister said.
For the package covering port equipment, the terminal operating system and security systems, a consortium of Japan's Mitsui E&S and Tec International is finalising designs. A factory survey was carried out in Japan in April.
On the package for boats and the vessel traffic management system, officials and a delegation from the Japan International Cooperation Agency agreed in September to consult bidders on narrowing the tender's scope to speed up procurement.
Source: The Business Standard · Source date: 2026-11-17.